| Beginning Construction Date |
Fall, 2005 |
| Completed Construction Date |
Spring, 2008 |
| Architect |
DPHS |
| Contractor |
Sletten |
| Project Budget |
$113.0 million |
| Construction Budget |
$70.4 million |
| Major Spaces |
Offices, Classrooms, Laboratories |